University Of Pune Question Paper
M. C. M. (Semester - III) Examination - 2012
SOFTWARE PROJECT MANAGEMENT
(New 2008 Pattern)
Time : 3 Hours] [Max. Marks : 70
Instructions :
(1) Question Nos. 1 is compulsory.
(2) Answer any five from remaining.
(3) Neat diagram carry marks.
(4) Q. No. 1 carries 20 marks. Remaining questions carry 10
marks each.
Q.1) (A) Draw PERT diagram by using following activities and calculate
Time Duration of each activity and find out critical path : [15]
Activity Precedents Optimistic Most Likely Pessimistic
Time (Hr.) Time (Hr.) Time (Hr.)
A – 4 6 8
B – 1 4.5 5
C A 3 3 3
D A 4 5 6
E A 0.5 1 1.5
F B, C 3 4 5
G B, C 1 1.5 5
H E, F 5 6 7
I E, F 2 5 8
J D, H 2.5 2.75 4.5
K G, I 3 5 7
(B) Explain Project Life Cycle. [05]
Q.2) What do you mean by Risk ? Explain Software Project Risk
Management in detail. [10]
Q.3) Write a detail note on Software Implementation. [10]
Q.4) Explain Software Project Maintenance in detail. [10]
Q.5) What do you mean by IT Operation Management ? Explain roles and
responsibility. [10]
Q.6) Explain SCM in detailed. [10]
Q.7) Write short notes : (Any Two) [10]
(a) Version Control
(b) Software Testing
(c) COCOMO
(d) QA Vs QC
M. C. M. (Semester - III) Examination - 2012
SOFTWARE PROJECT MANAGEMENT
(New 2008 Pattern)
Time : 3 Hours] [Max. Marks : 70
Instructions :
(1) Question Nos. 1 is compulsory.
(2) Answer any five from remaining.
(3) Neat diagram carry marks.
(4) Q. No. 1 carries 20 marks. Remaining questions carry 10
marks each.
Q.1) (A) Draw PERT diagram by using following activities and calculate
Time Duration of each activity and find out critical path : [15]
Activity Precedents Optimistic Most Likely Pessimistic
Time (Hr.) Time (Hr.) Time (Hr.)
A – 4 6 8
B – 1 4.5 5
C A 3 3 3
D A 4 5 6
E A 0.5 1 1.5
F B, C 3 4 5
G B, C 1 1.5 5
H E, F 5 6 7
I E, F 2 5 8
J D, H 2.5 2.75 4.5
K G, I 3 5 7
(B) Explain Project Life Cycle. [05]
Q.2) What do you mean by Risk ? Explain Software Project Risk
Management in detail. [10]
Q.3) Write a detail note on Software Implementation. [10]
Q.4) Explain Software Project Maintenance in detail. [10]
Q.5) What do you mean by IT Operation Management ? Explain roles and
responsibility. [10]
Q.6) Explain SCM in detailed. [10]
Q.7) Write short notes : (Any Two) [10]
(a) Version Control
(b) Software Testing
(c) COCOMO
(d) QA Vs QC